What happens if the developer goes bankrupt?

If a developer fails before your home is finished, your guaranteed payments can be recovered from the bank or insurer, with interest. The home itself is a different question. Here is how the protection works, its limits, and how to act.

By Investidad advisory team · Last reviewed 16 Oct 2026

Your money and your home are two separate questions

Spain's off-plan rules were written with developer failure in mind. They protect the money you pay before completion. They do not guarantee that the home will be built, so the question is usually how to get your money back, not how to get the keys.

BEFORE COMPLETION

Every stage payment guaranteed

Money you pay before completion must be covered by an aval bancario or insurance and paid into a special account used only for the construction. If the home is not built or not finished on time, you are repaid with interest.

Ask for an individual certificate in your name for each payment. Your lawyer should check it before you pay.

AFTER COMPLETION
  • 10Structure · 10 yearsFoundations, beams, slabs and load-bearing walls, backed by the compulsory seguro decenal.
  • 3Installations · 3 yearsDefects that affect habitability: waterproofing, plumbing, electrics, insulation.
  • 1Finishes · 1 yearPaint, tiling, carpentry and fittings, claimed from the builder.

Liability periods under art. 17 of Ley 38/1999 (LOE), counted from the formal acceptance of the works. How guarantees and warranties work

Your payments: the guarantee

Under the first additional provision of the LOE, every payment made before completion must be guaranteed by an aval bancario or surety insurance and paid into a special account. The guarantee covers repayment of what you paid, including taxes, plus legal interest, if construction does not start or is not finished on time.

The claim is against the bank or insurer, not only the developer, so it does not depend on what the developer can pay. In practice you cancel the contract and demand repayment from the developer; if it does not repay within 30 days, you claim from the insurer, which must pay within 30 days. With a bank guarantee, act within two years of the developer's breach, or the guarantee lapses.

When the guarantee is missing

Buyers sometimes discover that no individual certificate was issued, or that money went into an ordinary account. Supreme Court case law has helped in both situations, though each case turns on its facts:

  • A collective policy without individual certificates: the Supreme Court has held that a bank or insurer that issued a collective guarantee for the project can be liable even where individual certificates were not issued.
  • Payments into the developer's ordinary account: in a judgment of 21 December 2015, the Supreme Court held that a bank that accepted buyers' payments into the developer's account without requiring a special account and guarantee is liable to the buyers for the amounts paid into it.
  • Who is protected: courts have treated the protection as aimed at buyers of a home to live in, including a second home; a buyer acting as a professional, for example buying to resell during construction, may be excluded unless the contract extends the protection.

Payments in cash, to an agent or outside the contract are much harder to recover. The safest course is still to pay only into the contract's special account and to hold a guarantee document for every payment.

Your contract and the home: insolvency proceedings

A developer that cannot pay its debts enters insolvency proceedings. Under Spain's Insolvency Act, the declaration of insolvency does not by itself end contracts in which both sides still have obligations, such as an unfinished purchase. The court-appointed administrator may try to finish and sell the project, sell it to another developer, or seek to end contracts.

Until the title deed is signed, you do not own the home, and a developer's construction loan is often registered on the plot, as a Nota simple will show. A refund claim against the developer itself ranks alongside other creditors in the proceedings, which is why the bank or insurer's guarantee matters so much.

Reducing the risk before you buy

Questions buyers ask

Will I get my money back if the developer goes bankrupt?
Payments covered by a valid guarantee can be recovered from the bank or insurer, with legal interest, if construction does not start or is not finished on time. Unguaranteed payments may only be recoverable as a claim in the insolvency, which is often slow and partial.
Can I still get the home?
Sometimes, if the administrator or a new developer completes the project. It is not guaranteed. Your lawyer can advise whether to keep the contract alive or cancel and claim under the guarantee, bearing the deadlines in mind.